A culture of hands-off management has derailed a $9.7 billion interagency weather satellite project, according to an inspector general’s testimony, and prompted several lawmakers to request the resignation of two senior officials at the National Oceanic and Atmospheric Administration.

Johnnie Frazier, the Commerce Department’s inspector general, testified last month that poor project oversight and excessive and inappropriate performance award fees caused more than $3 billion in cost overruns and a 17-month delay in launching the National Polar-orbiting Operational Environmental Satellite System (NPOESS). That news led House Science Committee members Reps. Bart Gordon (D-Tenn.) and David Wu (D-Ore.) to request the resignation of retired Vice Adm. Conrad Lautenbacher, undersecretary of Commerce for oceans and atmosphere, and his deputy undersecretary, retired Gen. John Kelly.

During a House Science Committee hearing May 11, Frazier said that senior government officials were disengaged from the project and failed to foresee that problems with a crucial sensor could delay launching the first NPOESS satellite. NOAA, the Defense Department and NASA are responsible for the NPOESS project. A committee comprising senior NOAA, DOD and NASA officials is charged with providing overall policy guidance and oversight.

NPOESS was supposed to be ready to launch its first satellite in March 2008. But during the 32-month period from May 2003 to December 2005, the senior-level oversight officials met formally only six times and did not meet at all from May to December 2003, even as monthly reports showed subcontractor delays related to the sensor.

Despite continuing reports about the project’s problems, the prime contractor, Northrop Grumman Space Technologies received more than $123 million in performance award fees, according to Frazier’s testimony. Those fees amounted to 84 percent of the available fee pool for the first six award periods. “We question the practice of paying award fees for performance rated ‘unsatisfactory’ by officials,” Frazier said.

The project’s senior leaders received a flogging during the hearing for not taking responsibility for their failures. Committee Chairman Rep. Sherwood Boehlert (R-N.Y.) said he was unhappy with NPOESS, which he described as “totally out of whack.” Boehlert said the committee would continue scrutinizing the project to ensure that the mistakes made in NPOESS are not repeated in NOAA’s next big satellite procurement.

John Pike, director of GlobalSecurity.org, which monitors space and military programs, said NPOESS might not be in a state of shambles had senior-level officials at NOAA and DOD assessed the project firsthand.

“Senior management needs to relearn the art of managing by walking around,” he said.

FCW in Print

In the latest issue: Looking back on three decades of big stories in federal IT.

Featured

  • FCW @ 30 GPS

    FCW @ 30

    Since 1996, FCW has covered it all -- the major contracts, the disruptive technologies, the picayune scandals and the many, many people who make federal IT function. Here's a look back at six of the most significant stories.

  • Shutterstock image.

    A 'minibus' appropriations package could be in the cards

    A short-term funding bill is expected by Sept. 30 to keep the federal government operating through early December, but after that the options get more complicated.

  • Defense Secretary Ash Carter speaks at the TechCrunch Disrupt conference in San Francisco

    DOD launches new tech hub in Austin

    The DOD is opening a new Defense Innovation Unit Experimental office in Austin, Texas, while Congress debates legislation that could defund DIUx.

  • Shutterstock image.

    Merged IT modernization bill punts on funding

    A House panel approved a new IT modernization bill that appears poised to pass, but key funding questions are left for appropriators.

  • General Frost

    Army wants cyber capability everywhere

    The Army's cyber director said cyber, electronic warfare and information operations must be integrated into warfighters' doctrine and training.

  • Rising Star 2013

    Meet the 2016 Rising Stars

    FCW honors 30 early-career leaders in federal IT.

Reader comments

Please post your comments here. Comments are moderated, so they may not appear immediately after submitting. We will not post comments that we consider abusive or off-topic.

Please type the letters/numbers you see above

More from 1105 Public Sector Media Group