4 lessons in rapid acquisition learned from DOD's new ATVs

The purchase of all-terrain vehicles provides lessons in how to shorten the procurement cycle

The urgent purchase of 16,000 armored all-terrain vehicles in 2007 was motivated by a desire to protect U.S. troops and prevent more casualties. But procurement experts say it could provide Defense Department officials with a template for making rapid acquisitions — if DOD sticks to some tried and true purchasing principles.

At the time of the purchase, DOD's goal was to get the Mine Resistant Ambush Protected (MRAP) vehicles to troops in Iraq and Afghanistan as quickly as possible.

However, DOD's strategy could apply to many situations in which the department needs to buy systems quickly, procurement experts told the House Armed Services Committee’s Defense Acquisition Reform panel on Oct. 8.

Four tactics in particular might be useful in other situations, they said:

  • Agree on a plan and stick to it. At the start of a rapid acquisition, officials must assess the immediate need and determine minimum requirements for the project, said Thomas Dee, director of the Joint Rapid Acquisition Cell at the Office of the Undersecretary of Defense for Acquisition, Technology and Logistics.

After officials have agreed on those requirements, they should not interrupt the acquisition and production processes to make changes, Dee said.

  • Stay with the familiar. At the outset of the MRAP program, DOD officials decided to use only proven technologies instead of testing new ones. They also kept requirements to a minimum with a strict policy of senior-level approval for any changes.

“That kept us from having to deal with requirements creep — with all the good ideas that people want to add later on — and allowed us to move forward very quickly,” said Brig. Gen. Michael Brogan, commander of the Marine Corps Systems Command.

  • Require bidders to show their work. DOD’s competition was full and open, but only road-ready contractors made the first cut. That is because DOD officials required vendors to bring in their vehicles and demonstrate their solutions, which weeded out the companies that had only plans, Brogan said.
  • Relieve vendors of some of the work, if possible. Officials made the government responsible for adding the final pieces of equipment, such as radios, to the vehicles after they were bought rather than putting those tasks on the contractor’s to-do list. That shortcut helped get the vehicles to the battlefield more quickly, said Michael Sullivan, director of acquisition and sourcing management at the Government Accountability Office.

Of course, in some ways, the MRAP procurement was a special case that made it easy to justify a different approach. First and foremost, lives were at stake. DOD was racing to respond to casualties caused by improvised explosive devices, which have accounted for as much as 75 percent of U.S. combat casualties in Iraq and Afghanistan.

To date, about $22.7 billion has been appropriated for the procurement of more than 16,000 MRAP vehicles, and Defense Secretary Robert Gates has said MRAP is DOD’s most important acquisition program.

The MRAP program followed a documented acquisition process, guided by DOD acquisition rules, Dee said.

Beyond the quick deal

Despite the success of the rapid approach in certain situations, DOD needs to invest more time and money in helping develop new technologies that could deal with future requirements, experts say.

The basis for accelerating the use of new technologies “is a robust research and development structure,” Dee said.

Sullivan agreed, saying DOD officials avoid working with immature technologies when they should be encouraging companies to develop vibrant and relevant solutions. DOD hasn’t done that in recent years, and as a result, it has had to include underdeveloped technology in acquisitions, which can inflate costs, he added.

If DOD were to make technology development a priority, “it could be a game changer in the acquisition process,” Sullivan said.

Meanwhile, acquisition changes are in the works. The House's defense panel will present a report to the full Armed Services Committee with recommendations for reforming DOD’s acquisition processes. Lawmakers will consider the recommendations for inclusion in DOD’s fiscal 2011 budget authorization legislation.

Panel Chairman Rep. Robert Andrews (D-N.J.) said the report will address improvements to the rapid acquisition process, including how to define urgency so officials can determine whether to use a special approach. The report will also discuss whether the MRAP approach can apply to traditional acquisitions.

About the Author

Matthew Weigelt is a freelance journalist who writes about acquisition and procurement.

The Fed 100

Save the date for 28th annual Federal 100 Awards Gala.

Featured

  • computer network

    How Einstein changes the way government does business

    The Department of Commerce is revising its confidentiality agreement for statistical data survey respondents to reflect the fact that the Department of Homeland Security could see some of that data if it is captured by the Einstein system.

  • Defense Secretary Jim Mattis. Army photo by Monica King. Jan. 26, 2017.

    Mattis mulls consolidation in IT, cyber

    In a Feb. 17 memo, Defense Secretary Jim Mattis told senior leadership to establish teams to look for duplication across the armed services in business operations, including in IT and cybersecurity.

  • Image from Shutterstock.com

    DHS vague on rules for election aid, say states

    State election officials had more questions than answers after a Department of Homeland Security presentation on the designation of election systems as critical U.S. infrastructure.

  • Org Chart Stock Art - Shutterstock

    How the hiring freeze targets millennials

    The government desperately needs younger talent to replace an aging workforce, and experts say that a freeze on hiring doesn't help.

  • Shutterstock image: healthcare digital interface.

    VA moves ahead with homegrown scheduling IT

    The Department of Veterans Affairs will test an internally developed scheduling module at primary care sites nationwide to see if it's ready to service the entire agency.

  • Shutterstock images (honglouwawa & 0beron): Bitcoin image overlay replaced with a dollar sign on a hardware circuit.

    MGT Act poised for a comeback

    After missing in the last Congress, drafters of a bill to encourage cloud adoption are looking for a new plan.

Reader comments

Please post your comments here. Comments are moderated, so they may not appear immediately after submitting. We will not post comments that we consider abusive or off-topic.

Please type the letters/numbers you see above

More from 1105 Public Sector Media Group