Fast contracts still face delays

A recent report by the Transportation Department's Inspector General found little correlation between the FAA's Acquisition Management System and contract implementation. Some of the contracts the FAA was awarding more quickly also experienced cost growth and schedule delays. The following chart is a sample of delays detailed in a DOT IG report.




ProgramPlanned program costs in millionsCost growth in millionsPlanned months to commissionMonths of schedule delay
Wide Area Augmentation System$1,006.6$632.64814
Standard Terminal Automation Replacement System940.2462.42849
Host and Oceanic Computer System Replacement Program442.50.081
Integrated Terminal Weather System276.10.0570
Integrated Terminal Weather System276.10.0570
Local-Area Augmentation System586.5134.8N/AN/A
Source: "Survey of the FAA's Integrated Product Development System," August 2000, DOT Inspector General

Featured

  • Government Innovation Awards
    Government Innovation Awards - https://governmentinnovationawards.com

    Congratulations to the 2021 Rising Stars

    These early-career leaders already are having an outsized impact on government IT.

  • Acquisition
    Shutterstock ID 169474442 By Maxx-Studio

    The growing importance of GWACs

    One of the government's most popular methods for buying emerging technologies and critical IT services faces significant challenges in an ever-changing marketplace

Stay Connected