GAO questions E-Authentication timetable

The General Services Administration’s timetable for building a gateway for the E-Authentication project is unrealistic, the General Accounting Office said yesterday.

GSA has reached few of its policy, procurement and technology objectives for E-Authentication, auditors said in the report, Planned E-Authentication Gateway Faces Formidable Development Challenges. “The modest progress achieved to date calls into question the likelihood that the project can successfully field an operational gateway, even within the revised schedule,” they said.

GSA originally expected to finish the gateway by last month, but the Office of Management and Budget extended the deadline to March 2004. E-Authentication is one of the five Quicksilver e-government projects managed by GSA and underlies plans for all 24 of the other Quicksilver projects.

Rep. Tom Davis (R-Va.), chairman of the Government Reform Committee, had asked GAO to examine the project. After seeing the report, he wrote to GSA administrator Stephen Perry requesting a meeting (Click for Oct. 15 GCN story).

The auditors said GSA must:

  • Establish policies for consistency and interoperability among different authentication systems, and develop technical standards.


  • Finish defining user authentication requirements for the 24 other e-government projects; GSA said 12 have been finished.


  • Deal with funding, security and privacy issues.


  • “We have serious concerns about the progress of the project,” said John de Ferrari, an assistant director in GAO’s Office of Information Management Issues. “Our biggest concern is with the amount of work that needs to be done to make the gateway really work. The idea of doing it extremely quickly in a matter of months seems to be unrealistic.”

    De Ferrari added that GAO does not believe the development work has been mishandled, but the agency should take the time necessary. Developing policy and achieving interoperability are GSA’s main hurdles, he said.

    About the Author

    Connect with the GCN staff on Twitter @GCNtech.

    Featured

    • Contracting
      8 prototypes of the border walls as tweeted by CBP San Diego

      DHS contractors face protests – on the streets

      Tech companies are facing protests internally from workers and externally from activists about doing for government amid controversial policies like "zero tolerance" for illegal immigration.

    • Workforce
      By Mark Van Scyoc Royalty-free stock photo ID: 285175268

      At OPM, Weichert pushes direct hire, pay agent changes

      Margaret Weichert, now acting director of the Office of Personnel Management, is clearing agencies to make direct hires in IT, cyber and other tech fields and is changing pay for specialized occupations.

    • Cloud
      Shutterstock ID ID: 222190471 By wk1003mike

      IBM protests JEDI cloud deal

      As the deadline to submit bids on the Pentagon's $10 billion, 10-year warfighter cloud deal draws near, IBM announced a legal protest.

    Stay Connected

    FCW Update

    Sign up for our newsletter.

    I agree to this site's Privacy Policy.