Air Force must do better job of tracking risky agreements: IG

Auditors found employees requested the agreements with insufficient supporting details and didn't adequately document risk-mitigation steps

Air Force contracting personnel often failed to complete all necessary steps to protect the service before letting a contractor begin a project even though negotiations were still under way, Defense Department auditors reported this week.

Officials at the Air Force Electronic Systems Center (ESC) need to keep tighter reins on contracting officers who issue risky undefinitized contract actions (UCAs), according to an Aug. 18 DOD inspector general report. The law allows for the pre-award agreements, which let a contractor start work and charge the government before the two parties have reached a final agreement on a contract's terms, specifications or price.

To a great extent, auditors found that ESC contracting officers had the necessary authorization and showed that prices were reasonable. However, the auditors came across 56 instances among the 41 UCAs they audited in which ESC employees did not fully comply with accompanying restrictions.


Related stories

Gates' DOD plans would shift CIO to DISA

Insourcing failed, DOD's Gates says. Now what?


ESC employees prepared requests to issue a UCA that provided insufficient detail to support the request, and they didn’t adequately document how they reduced the Air Force's risk by limiting the company’s profit, the report states.

“If the contractor’s reduced risk is not reflected in the negotiated profit rate, then the government could be paying too much profit to the contractor,” auditors wrote.

Furthermore, ESC staff didn't consistently manage the UCAs. Contracting employees issued agreements based on inadequate requests, and they did not appropriately define the agreements within six months as required, the report states.

The report recommends that officials establish procedures to make sure employees fully document UCAs. The report also urges officials to ensure that UCA requests include details on the adverse effects on the agency if the contracting employees don’t issue the UCA. Air Force officials agreed with the recommendations.

About the Author

Matthew Weigelt is a freelance journalist who writes about acquisition and procurement.

Featured

  • IT Modernization
    shutterstock image By enzozo; photo ID: 319763930

    OMB provides key guidance for TMF proposals amid surge in submissions

    Deputy Federal CIO Maria Roat details what makes for a winning Technology Modernization Fund proposal as agencies continue to submit major IT projects for potential funding.

  • gears and money (zaozaa19/Shutterstock.com)

    Worries from a Democrat about the Biden administration and federal procurement

    Steve Kelman is concerned that the push for more spending with small disadvantaged businesses will detract from the goal of getting the best deal for agencies and taxpayers.

Stay Connected