GAO will finish its bid protest work

The Government Accountability Office ruled on June 14 that it will not reject a bid protest against a task or delivery order if it was filed before May 27, when the authority expired.

“We do not view the sunset provision as applying to pending protests,” according to a newly released bid protest decision.


Related story:

Expired protest authority might change spending habits


GAO decided against the Defense Information Systems Agency's argument to dismiss a protest by Technatomy Corp. The company objected to the evaluation of a task order that DISA awarded to Catapult Technology, Inc. for support of the Army Information Technology Agency.

DISA contended that GAO's authority to review the bid protest ended on May 27, leaving Technatomy’s protest out of bounds.

However, GAO argued that it needs to finish its work of judging bid protests.

"Even if we were to view the sunset provision as barring our jurisdiction as of May 27, 2011, as DISA argues, it would not end our jurisdiction to complete our review of protests filed with our office prior to the effective date of the sunset,” GAO wrote.

About the Author

Matthew Weigelt is a freelance journalist who writes about acquisition and procurement.

Featured

  • Management
    shutterstock image By enzozo; photo ID: 319763930

    Where does the TMF Board go from here?

    With a $1 billion cash infusion, relaxed repayment guidelines and a surge in proposals from federal agencies, questions have been raised about whether the board overseeing the Technology Modernization Fund has been scaled to cope with its newfound popularity.

  • IT Modernization
    shutterstock image By enzozo; photo ID: 319763930

    OMB provides key guidance for TMF proposals amid surge in submissions

    Deputy Federal CIO Maria Roat details what makes for a winning Technology Modernization Fund proposal as agencies continue to submit major IT projects for potential funding.

Stay Connected