GSA cloud transition questioned in audit report

General Services Administration officials have not properly assessed the headway they’ve made in transitioning GSA from Lotus Notes to the cloud, according to a new report.

Either the performance measures used to track the progress towards each of the project’s goals are unclear, the GSA inspector general reported Sept. 28, or the project simply lacks real targets. And if targets were set, officials did not adjust them to reflect the current environment.

For example, the IG found that GSA’s Office of Chief Information Officer did not update the cost analysis to reflect its efforts to decrease in-house maintenance burdens by reducing email support staff. And while the CIO projected the transition would save $15 million over five years, officials did not update the support-cost analysis with either their estimates of future benefits or their cost comparisons.


Read the IG report


Office of Management and Budget rules state that agencies must establish, and then validate, a performance-measurement baseline with clear cost, schedule and performance goals.

GSA’s move from Lotus Notes to the cloud is part of the Cloud First policy set forth in December 2010 by then-U.S. CIO Vivek Kundra. That same month, GSA signed a contract to migrate its email to the cloud, and in 2011 became the first agency to transition its entire e-mail stack.

Besides the blurry targets and savings figures, the CIO did not create sufficient controls to ensure GSA was not migrating redundant applications to the cloud, the report states. GSA’s Lotus Notes contains thousands of applications, many of which were redundant or dormant, and were maintained at 17 different GSA locations.

Officials initially used a decentralized approach to finding like applications before moving them to the cloud, but later found it necessary to create a center of excellence to review for redundancies every request to build an application.

In all, the IG could not determine whether or not GSA, in fact, was making adequate progress in meeting its goals for saving money.  The report recommended that officials clarify performance measures and redouble their hunt for duplicative applications.

Furthermore, the IG wrote that officials should prepare an updated project savings justification regarding email and collaboration tools by using actual figures.

GSA’s CIO Casey Coleman, in a Sept. 12 letter to the IG that was included as an appendix to the report, said agreed with the finding and recommendations.  She did not specify when or how those recommendations might be implemented.

 

 

About the Author

Matthew Weigelt is a freelance journalist who writes about acquisition and procurement.

Featured

  • Defense
    Ryan D. McCarthy being sworn in as Army Secretary Oct. 10, 2019. (Photo credit: Sgt. Dana Clarke/U.S. Army)

    Army wants to spend nearly $1B on cloud, data by 2025

    Army Secretary Ryan McCarthy said lack of funding or a potential delay in the JEDI cloud bid "strikes to the heart of our concern."

  • Congress
    Rep. Jim Langevin (D-R.I.) at the Hack the Capitol conference Sept. 20, 2018

    Jim Langevin's view from the Hill

    As chairman of of the Intelligence and Emerging Threats and Capabilities subcommittee of the House Armed Services Committe and a member of the House Homeland Security Committee, Rhode Island Democrat Jim Langevin is one of the most influential voices on cybersecurity in Congress.

Stay Connected

FCW INSIDER

Sign up for our newsletter.

I agree to this site's Privacy Policy.