Review team recommends ‘gap-filler’ satellite program

Geostationary Operational Environmental Satellites - NOAA

The National Oceanic and Atmospheric Administration should begin procuring atmospheric sounding instruments immediately and attach them to a “gap-filler” satellite to help mitigate a pending gap in polar-orbiting weather satellite coverage, according to a federally commissioned independent review team.

The recommendations were made Nov. 14 in a report evaluating NOAA’s two major satellite programs and are aimed at mitigating a potentially catastrophic gap in polar satellite coverage around 2016, when existing polar satellites are expected to fail.

The first of NOAA’s next-generation polar satellites -- Joint Polar Satellite System-1 (JPSS-1) – will not launch until 2017, and any launch or operational issues the satellite has could extend a gap in data until at least 2021, when its sibling satellite, JPSS-2, is launched. Over its life cycle, JPSS will cost about $11 billion.

“A gap-filler project must be started immediately as a hedge against the early potential gap,” the report states.

The report calls for NOAA to procure multiple units of the Advanced Technology Microwave Sounder and the Cross-track Infrared Sounder under contract with current developers, and attach them to a satellite smaller and cheaper than JPSS.

The report states that “an expedited decision and procurement process” could allow NOAA and NASA to launch a gap-filler satellite into low Earth orbit within three years if the process begins immediately.

However, even if NOAA accepts the recommendations -- and Mary Kicza, assistant administrator of NOAA's Satellite and Information Service, said the agency takes them very seriously -- such a gap-filler program would face major hurdles.  

The Satellite and Information Service spends approximately $2.2 billion a year but would require additional appropriations from Congress in short order to pursue a satellite acquisition to fill the potential weather gap.

NOAA’s relationship with Congress has been marred by cost overruns and delays dating back to the early 2000s, when NOAA, NASA and the Defense Department spent billions on the National Polar-orbiting Operational Environmental Satellite System that produced one viable satellite before the program was disbanded. That single success, Suomi NPP, is the polar-orbiting satellite now producing afternoon orbital data for NOAA, but it is not expected to last beyond 2016.  

Thomas Young, chairman of the independent review team, said the urgent nature of such a satellite system should trump congressional resistance. He stressed that even if NOAA and NASA were to get such a system into orbit by 2017, it would not entirely eliminate the risk of a gap, although it would strengthen NOAA’s satellite program moving forward.

“The absence of JPSS data due to a gap could potentially be catastrophic,” Young said. “Even if it started today, such a program could not totally protect against a gap. The current JPSS program is very fragile and needs to be made more robust."

 

LINKS: http://fcw.com/articles/2013/11/14/noaa-satellite-programs-earn-mixed-reviews.aspx - yesterday’s piece on this

About the Author

Frank Konkel is a former staff writer for FCW.

The Fed 100

Read the profiles of all this year's winners.

Featured

  • Then-presidential candidate Donald Trump at a 2016 campaign event. Image: Shutterstock

    'Buy American' order puts procurement in the spotlight

    Some IT contractors are worried that the "buy American" executive order from President Trump could squeeze key innovators out of the market.

  • OMB chief Mick Mulvaney, shown here in as a member of Congress in 2013. (Photo credit Gage Skidmore/Flickr)

    White House taps old policies for new government makeover

    New guidance from OMB advises agencies to use shared services, GWACs and federal schedules for acquisition, and to leverage IT wherever possible in restructuring plans.

  • Shutterstock image (by Everett Historical): aerial of the Pentagon.

    What DOD's next CIO will have to deal with

    It could be months before the Defense Department has a new CIO, and he or she will face a host of organizational and operational challenges from Day One

  • USAF Gen. John Hyten

    General: Cyber Command needs new platform before NSA split

    U.S. Cyber Command should be elevated to a full combatant command as soon as possible, the head of Strategic Command told Congress, but it cannot be separated from the NSA until it has its own cyber platform.

  • Image from Shutterstock.

    DLA goes virtual

    The Defense Logistics Agency is in the midst of an ambitious campaign to eliminate its IT infrastructure and transition to using exclusively shared, hosted and virtual services.

  • Fed 100 logo

    The 2017 Federal 100

    The women and men who make up this year's Fed 100 are proof positive of what one person can make possibile in federal IT. Read on to learn more about each and every winner's accomplishments.

Reader comments

Please post your comments here. Comments are moderated, so they may not appear immediately after submitting. We will not post comments that we consider abusive or off-topic.

Please type the letters/numbers you see above

More from 1105 Public Sector Media Group