Testing of IT options for the 2020 census might not be completed before the Census Bureau has to decide on the operational design of the decennial count. Bureau officials plan to make that call in September 2015.

Although the agency has made progress in research and testing the IT it plans to use, several of the supporting projects have neither a schedule nor a detailed plan, according to a Government Accountability Office report released April 3.

GAO auditors said the bureau has begun research on six IT-related projects, including a proposal to use the Internet for survey response, for which the bureau has been buying up URLs, and allowing census workers to use their own mobile devices to collect data. The goal is to have at least 60 percent of responses submitted electronically, which should drive down costs for postage, paper and staff time, Census Bureau CIO Brian McGrath told FCW late last year.

But four of the six projects do not have finalized schedules, three have no plan for gauging progress, and the two projects that do have schedules are not expected to be completed until after the September 2015 decision on the census' design, GAO said.

The decision must be made around the midpoint of the 10-year cycle so that the acquisition process can begin in fiscal 2017 or 2018 and allow provide plenty of time to test and deploy equipment.

GAO also criticized the Census Bureau for failing to determine which projects are the most important to complete before the decision on deployment must be made.

"Officials stated that they are working with project teams to determine what needs to be completed and by when to support the design decision, but as of December 2013 they had not specified when this would be completed," the report states. "Without prioritizing its projects and establishing schedules and plans, the bureau risks not making a timely and well-informed design decision for the 2020 census."

The bureau has identified potential risks with its IT programs "but has not consistently developed mitigation plans for all of them," GAO auditors wrote.

They recommended that the bureau set priorities for its IT-related research and testing projects and develop project schedules to reflect those priorities. The Commerce Department, of which the Census Bureau is a component, concurred with GAO's recommendations and said it had already begun to address them.

About the Author

John Bicknell is a former executive editor of FCW, and the author of America 1844: Religious Fervor, Westward Expansion, and the Presidential Election That Transformed the Nation.

FCW in Print

In the latest issue: Looking back on three decades of big stories in federal IT.


  • Anne Rung -- Commerce Department Photo

    Exit interview with Anne Rung

    The government's departing top acquisition official said she leaves behind a solid foundation on which to build more effective and efficient federal IT.

  • Charles Phalen

    Administration appoints first head of NBIB

    The National Background Investigations Bureau announced the appointment of its first director as the agency prepares to take over processing government background checks.

  • Sen. James Lankford (R-Okla.)

    Senator: Rigid hiring process pushes millennials from federal work

    Sen. James Lankford (R-Okla.) said agencies are missing out on younger workers because of the government's rigidity, particularly its protracted hiring process.

  • FCW @ 30 GPS

    FCW @ 30

    Since 1987, FCW has covered it all -- the major contracts, the disruptive technologies, the picayune scandals and the many, many people who make federal IT function. Here's a look back at six of the most significant stories.

  • Shutterstock image.

    A 'minibus' appropriations package could be in the cards

    A short-term funding bill is expected by Sept. 30 to keep the federal government operating through early December, but after that the options get more complicated.

  • Defense Secretary Ash Carter speaks at the TechCrunch Disrupt conference in San Francisco

    DOD launches new tech hub in Austin

    The DOD is opening a new Defense Innovation Unit Experimental office in Austin, Texas, while Congress debates legislation that could defund DIUx.

Reader comments

Wed, Apr 9, 2014

SoWhatElseIsNew Maryland sounds like a typical Government worker covered by a union that expects everything to be given to them. What? You applied for a position and were denied because of your lack of ability? Stop complaining and be part of the solution!

Fri, Apr 4, 2014 SoWhatElseIsNew Maryland

I've been at the Census Bureau for some time and the way things are done in IT has not change. You bring in new technology, but we're using old processes. You have the same old good ol' boy/girl network who can't lead or do the job. The VDI project is a disgrace along with SharePoint 2010. Employees are micro-managed and not empowered. No training is provided and you're left on your own to figure out how to perform a task which you've never done before. Contractors walk around like they own the place. Every year with the end of fiscal year spend or lose funds, massive amounts of software/hardware are purchased, but eventually they sit and collect dust. Good luck GAO. I read your report every year, but it's always the same. It boils down to poor management/leadership. If you want to see results, hire/promote veterans into management/leadership positions.

Please post your comments here. Comments are moderated, so they may not appear immediately after submitting. We will not post comments that we consider abusive or off-topic.

Please type the letters/numbers you see above

More from 1105 Public Sector Media Group