Homeland Security

St. Elizabeth's campus again at issue on Capitol Hill

Coast Guard All Hands Blog image: St. Elizabeth's campus.

The Coast Guard is the only DHS component that has fully migrated its HQ to the St. Elizabeth's campus.

The Department of Homeland Security's massive headquarters under construction at the old St. Elizabeth's Hospital site in Washington, D.C., remains either a gigantic waste of money or a model investment that could save the federal government hundreds of millions of dollars in the long term, depending on who you ask.

"Sometimes as a nation, we can be penny-wise and pound foolish. This is a project that exemplifies that," House Homeland Security Management and Oversight Subcommittee Chairman Jeff Duncan said at a Sept. 19 hearing.

The South Carolina Republican took issue with some of the project’s "cushy" features, including Brazilian hardwood used in the Coast Guard's headquarters buildings at the site, rainwater toilets and eco-friendly roofs. He said DHS had not given the project the necessary oversight and urged the Senate to act on his acquisition reform bill, which the House passed by voice vote in June.

The project, which aims to combine headquarters sites for DHS's 22 component agencies, has had a rocky history with lawmakers since DHS began work in 2009 on the 770-acre campus in southeast Washington. The Coast Guard is the only DHS component that has fully relocated, and has 3,200 employees working at the site.

A Government Accountability Office study unveiled at the House hearing said DHS and the General Services Administration hadn't followed relevant GSA guidance and GAO's leading practices when developing the cost and schedule estimates for the project, that cost estimates were unreliable, and that Congress should consider withholding future funding until those problems are addressed.

The GAO study contained a table that shows the completion deadline for the project is 11 years behind the original schedule, and if completed by the current 2026 target date could cost a total of $4.5 billion.

At the same time as the House hearing, the chairman of the Senate Homeland Security and Governmental Affairs Committee was praising the project as a long-term money saver.

Sen. Tom Carper (D-Del.) issued a report that said the headquarters project would improve security and save the federal government almost $1 billion.

DHS operates out of more than 50 separate facilities in the D.C. area, many of which are physically inadequate, according to Carper. The current infrastructure used to house the department, he said, has made it much more difficult to implement the vision behind the Homeland Security Act and create the collaborative approach envisioned.

The consolidation, said Carper, would improve the agency's crisis management by allowing better collaboration and interaction among personnel during crises, as well as making it physically easier for them to work together.

The Senate report also claimed that the federal government would save nearly $700 million over 30 years by completing and moving DHS into a consolidated campus headquarters.

About the Author

Mark Rockwell is a senior staff writer at FCW, whose beat focuses on acquisition, the Department of Homeland Security and the Department of Energy.

Before joining FCW, Rockwell was Washington correspondent for Government Security News, where he covered all aspects of homeland security from IT to detection dogs and border security. Over the last 25 years in Washington as a reporter, editor and correspondent, he has covered an increasingly wide array of high-tech issues for publications like Communications Week, Internet Week, Fiber Optics News, tele.com magazine and Wireless Week.

Rockwell received a Jesse H. Neal Award for his work covering telecommunications issues, and is a graduate of James Madison University.

Click here for previous articles by Rockwell. Contact him at mrockwell@fcw.com or follow him on Twitter at @MRockwell4.


Featured

  • FCW PERSPECTIVES
    sensor network (agsandrew/Shutterstock.com)

    Are agencies really ready for EIS?

    The telecom contract has the potential to reinvent IT infrastructure, but finding the bandwidth to take full advantage could prove difficult.

  • People
    Dave Powner, GAO

    Dave Powner audits the state of federal IT

    The GAO director of information technology issues is leaving government after 16 years. On his way out the door, Dave Powner details how far govtech has come in the past two decades and flags the most critical issues he sees facing federal IT leaders.

  • FCW Illustration.  Original Images: Shutterstock, Airbnb

    Should federal contracting be more like Airbnb?

    Steve Kelman believes a lighter touch and a bit more trust could transform today's compliance culture.

Stay Connected

FCW Update

Sign up for our newsletter.

I agree to this site's Privacy Policy.