SBInet faces construction delays

Budget concerns and the need to test the multibillion-dollar border-surveillance system in the laboratory could stall new building for months.

The Homeland Security Department probably will not resume construction of its multibillion-dollar border-surveillance system until January 2009 even if federal land permits are approved before then, a spokesman said today.

Budget concerns and the need to test the technology in the laboratory are likely to delay SBInet’s deployment for four or five months, said Michael Friel, a spokesman for Customs and Border Protection.

The agency has completed about half of the 670 miles of pedestrian fencing and vehicle barriers it aims to build this year, and agency officials are considering whether to redirect SBInet funding to cover the dramatically rising costs of steel, fuel and other items involved in fence construction in the Southwestern United States, Friel said.

“Considering the need to test the technology [for SBInet] and to complete that testing, the idea is that the deployment dollars set aside for SBInet could be used to help offset the fencing costs,” Friel said.

Work was scheduled to begin this summer on the first permanent SBInet towers, which would hold cameras, radar units, sensors and communications equipment. The permanent towers would replace mobile structures erected during the 28-mile prototype phase of the project in Arizona, which was completed in February.

On Aug. 19, CBP officials confirmed that they had ordered prime contractor Boeing to halt work on SBInet’s virtual fence until the agency received land-use and environmental permissions from the Interior Department.

Three days later, the agency received a partial go-ahead when Interior's Fish and Wildlife Service announced that it was granting preliminary approval for five SBInet towers on the Buenos Aires National Wildlife Refuge in Arizona. Final permission could come as early as Sept. 8.

Seventeen towers are planned for the Tucson-1 segment of the SBInet project that was to begin construction this summer, Friel said. Four towers are already built. A second segment, called Ajo-1, calls for 11 towers.

Although the permits could be approved soon, CBP and Boeing intend to spend the next several weeks or months testing the networks, communications and sensors in a laboratory setting and evaluating how well they work together, Friel said. Formal system testing will follow the preliminary tests.

“We are working to complete those tests prior to deployment,” Friel said. “No date has been set, but we are looking at January 2009.”

The need for laboratory tests was discussed earlier this year after the deployment of the 28-mile prototype phase of the project. Border patrol officials and federal auditors expressed concern about some features of the prototype system, which were delayed and did not work as well as anticipated.

SBInet is one of DHS’ most ambitious technology projects. Its ultimate goal is to secure the U.S. borders with Mexico and Canada, and its costs could exceed $30 billion.

The Bush administration has requested $775 million for SBInet in its fiscal 2009 budget.

NEXT STORY: GSA names technology executive

X
This website uses cookies to enhance user experience and to analyze performance and traffic on our website. We also share information about your use of our site with our social media, advertising and analytics partners. Learn More / Do Not Sell My Personal Information
Accept Cookies
X
Cookie Preferences Cookie List

Do Not Sell My Personal Information

When you visit our website, we store cookies on your browser to collect information. The information collected might relate to you, your preferences or your device, and is mostly used to make the site work as you expect it to and to provide a more personalized web experience. However, you can choose not to allow certain types of cookies, which may impact your experience of the site and the services we are able to offer. Click on the different category headings to find out more and change our default settings according to your preference. You cannot opt-out of our First Party Strictly Necessary Cookies as they are deployed in order to ensure the proper functioning of our website (such as prompting the cookie banner and remembering your settings, to log into your account, to redirect you when you log out, etc.). For more information about the First and Third Party Cookies used please follow this link.

Allow All Cookies

Manage Consent Preferences

Strictly Necessary Cookies - Always Active

We do not allow you to opt-out of our certain cookies, as they are necessary to ensure the proper functioning of our website (such as prompting our cookie banner and remembering your privacy choices) and/or to monitor site performance. These cookies are not used in a way that constitutes a “sale” of your data under the CCPA. You can set your browser to block or alert you about these cookies, but some parts of the site will not work as intended if you do so. You can usually find these settings in the Options or Preferences menu of your browser. Visit www.allaboutcookies.org to learn more.

Sale of Personal Data, Targeting & Social Media Cookies

Under the California Consumer Privacy Act, you have the right to opt-out of the sale of your personal information to third parties. These cookies collect information for analytics and to personalize your experience with targeted ads. You may exercise your right to opt out of the sale of personal information by using this toggle switch. If you opt out we will not be able to offer you personalised ads and will not hand over your personal information to any third parties. Additionally, you may contact our legal department for further clarification about your rights as a California consumer by using this Exercise My Rights link

If you have enabled privacy controls on your browser (such as a plugin), we have to take that as a valid request to opt-out. Therefore we would not be able to track your activity through the web. This may affect our ability to personalize ads according to your preferences.

Targeting cookies may be set through our site by our advertising partners. They may be used by those companies to build a profile of your interests and show you relevant adverts on other sites. They do not store directly personal information, but are based on uniquely identifying your browser and internet device. If you do not allow these cookies, you will experience less targeted advertising.

Social media cookies are set by a range of social media services that we have added to the site to enable you to share our content with your friends and networks. They are capable of tracking your browser across other sites and building up a profile of your interests. This may impact the content and messages you see on other websites you visit. If you do not allow these cookies you may not be able to use or see these sharing tools.

If you want to opt out of all of our lead reports and lists, please submit a privacy request at our Do Not Sell page.

Save Settings
Cookie Preferences Cookie List

Cookie List

A cookie is a small piece of data (text file) that a website – when visited by a user – asks your browser to store on your device in order to remember information about you, such as your language preference or login information. Those cookies are set by us and called first-party cookies. We also use third-party cookies – which are cookies from a domain different than the domain of the website you are visiting – for our advertising and marketing efforts. More specifically, we use cookies and other tracking technologies for the following purposes:

Strictly Necessary Cookies

We do not allow you to opt-out of our certain cookies, as they are necessary to ensure the proper functioning of our website (such as prompting our cookie banner and remembering your privacy choices) and/or to monitor site performance. These cookies are not used in a way that constitutes a “sale” of your data under the CCPA. You can set your browser to block or alert you about these cookies, but some parts of the site will not work as intended if you do so. You can usually find these settings in the Options or Preferences menu of your browser. Visit www.allaboutcookies.org to learn more.

Functional Cookies

We do not allow you to opt-out of our certain cookies, as they are necessary to ensure the proper functioning of our website (such as prompting our cookie banner and remembering your privacy choices) and/or to monitor site performance. These cookies are not used in a way that constitutes a “sale” of your data under the CCPA. You can set your browser to block or alert you about these cookies, but some parts of the site will not work as intended if you do so. You can usually find these settings in the Options or Preferences menu of your browser. Visit www.allaboutcookies.org to learn more.

Performance Cookies

We do not allow you to opt-out of our certain cookies, as they are necessary to ensure the proper functioning of our website (such as prompting our cookie banner and remembering your privacy choices) and/or to monitor site performance. These cookies are not used in a way that constitutes a “sale” of your data under the CCPA. You can set your browser to block or alert you about these cookies, but some parts of the site will not work as intended if you do so. You can usually find these settings in the Options or Preferences menu of your browser. Visit www.allaboutcookies.org to learn more.

Sale of Personal Data

We also use cookies to personalize your experience on our websites, including by determining the most relevant content and advertisements to show you, and to monitor site traffic and performance, so that we may improve our websites and your experience. You may opt out of our use of such cookies (and the associated “sale” of your Personal Information) by using this toggle switch. You will still see some advertising, regardless of your selection. Because we do not track you across different devices, browsers and GEMG properties, your selection will take effect only on this browser, this device and this website.

Social Media Cookies

We also use cookies to personalize your experience on our websites, including by determining the most relevant content and advertisements to show you, and to monitor site traffic and performance, so that we may improve our websites and your experience. You may opt out of our use of such cookies (and the associated “sale” of your Personal Information) by using this toggle switch. You will still see some advertising, regardless of your selection. Because we do not track you across different devices, browsers and GEMG properties, your selection will take effect only on this browser, this device and this website.

Targeting Cookies

We also use cookies to personalize your experience on our websites, including by determining the most relevant content and advertisements to show you, and to monitor site traffic and performance, so that we may improve our websites and your experience. You may opt out of our use of such cookies (and the associated “sale” of your Personal Information) by using this toggle switch. You will still see some advertising, regardless of your selection. Because we do not track you across different devices, browsers and GEMG properties, your selection will take effect only on this browser, this device and this website.